Onnens Motorway A5
发布时间:2018-11-23 浏览次数:878 来源:永利y23455
The cross-section of the tunnel consists of two concrete vaults. The length of the tunnel is 1230 m.
Image Onnens Motorway A5

 
The aim of the monitoring was to increase knowledge on the vaults behaviour during the outer filling loads application. 30 sensors were installed on one characteristic section. Fiber optic sensors are integrated in the global concept together with inclinometers, thermometers, load cells, piezometer cells and geometric measurement. 

INSTALLATION PERIOD TYPE OF SENSORS NUMBER OF SENSORS
2000 – 2003 SOFO 6




Aim of monitoring:

Behaviour and stabilization of the cut and cover tunnel has been verified at each phases of the filling.
 
ImageGlobal view
ImageFiber optic sensor and inclinometer in the central section
ImageConnection box integrated in the framework
ImageFinal connection box after the removal of the framework on a technical gallery
 